How to price a wholesale contract
The wholesale contract price is not a percent of ARV and not a discount you felt out on the porch. It is the end buyer’s maximum allowable offer minus the fee you need, and only when that result is still at or above zero. This page uses a different invented deal from the checklist so the two pages do not repeat one worksheet. After-repair value is $180,000. Rehab is $22,000. The checklist used $210,000 and $35,000. Do not mix the totals.
The ceiling
Profit is 25 percent of $180,000, which is $45,000. Closing is 5 percent, which is $9,000. Holding is 3 percent, which is $5,400. The maximum allowable offer is $180,000 minus $22,000 minus $45,000 minus $9,000 minus $5,400, which is $98,600. The 70 percent screen is $126,000 minus $22,000, which is $104,000. This page prices the contract from $98,600. If your buyer truly stops at $104,000, you are on a different ceiling and you should say so before you subtract a fee. The MAO calculator prints $98,600 from these inputs. The ARV and 70% rule calculator prints the $104,000 if you give it a median of $180,000 and rehab of $22,000.
The fee you need
The fee is an invented $8,000. The highest contract is $98,600 minus $8,000, which is $90,600. Sign at $90,600 and the spread under the ceiling is the $8,000, if the buyer’s ceiling holds and the rehab holds. Sign at $94,000 because the seller named that floor, and the spread is $98,600 minus $94,000, which is $4,600. You did not get an $8,000 fee with a harder conversation. You got a $4,600 fee. The missing $3,400 has to come off the contract, off the fee target, or out of a ceiling you can defend. It does not come from calling $4,600 “about eight.”
A contract at $98,600 leaves a fee of zero. A contract at $100,000 is $1,400 over the ceiling, so the fee is not a small positive number. There is no fee. The buyer who pays $98,600 and not a dollar more cannot also pay your spread. The 70 percent examples are what the shorter screen does on other ARVs. They are not permission to switch this deal’s ceiling to $104,000 in the last paragraph because $90,600 was unpopular.
What has to be true before $90,600 is a price
The $180,000 has to be a median you can explain, and the $22,000 has to be a scope you can hand the buyer. A fee calculated on a hopeful ARV is a fee the buyer will re-trade. The ARV estimate is the median-versus-average step. If a fourth comp would have moved $180,000, it moves $90,600 by the same dollars, because the fee was a fixed $8,000 and the contract is a remainder. Rehab that becomes $30,000 instead of $22,000 drops the ceiling by $8,000, to $90,600, and the highest contract for an $8,000 fee drops to $82,600. The whole contingency came out of the contract. That is the correct direction. Hiding it inside a fatter ARV is not.
Assignment is how you get paid if the contract allows it. This page does not choose your clause. It chooses the price at which an $8,000 assignment still fits under $98,600, and it shows the $4,600 that fits under a $94,000 floor. Both numbers are invented checks. They are not an offer to a seller.
Questions
Why is the highest contract $90,600?
The 25/5/3 offer is $98,600. The fee you want is $8,000. $98,600 minus $8,000 is $90,600. A higher contract is a smaller fee, not the same fee.
What does a $94,000 seller floor do to an $8,000 fee?
The fee that fits is $98,600 minus $94,000, which is $4,600. You are $3,400 short of $8,000. The floor did not move the buyer’s ceiling.
run a full analysis free when the median you can do by hand is not enough. A full analysis weights the comps, adjusts beds and baths, and prices the repair tiers. The sample figures there are invented, the same way every dollar on this page is invented.